Collington Lane West, Bexhill - Carriageway Surfacing

21-27 July 2022

Scheme Location:


Collington Lane West, Bexhill - Carriageway Surfacing

Scheme Information:

What works are taking place?

We will be carrying out micro asphalt surfacing works on Collington Lane West, Bexhill.

Micro asphalt is a thin surfacing that is mixed in a lorry and laid on top of the existing road surface.

Micro asphalt seals and waterproofs the road and improves the skid resistance and ride quality, extending the life of the road by up 10 years.

We will return around two weeks after the micro-asphalt has been laid to raise any iron work that is low and reinstate any lining.

When will these works start?

Work will take place 21-27 June (no weekend working).

If it rains or is either too hot (temperatures over around 30°C) or too cold (temperatures below around 10°C) then we will not be able to carry out the work. We will reschedule these and let you know via the signs on site as to when the works will happen.

BT will be adjusting their manholes following the surfacing works. This work will take place from 22 to 26 August between 8am and 5pm each. The road will be closed during this time.

Road closure information

Collington Lane West will be closed between 7am and 7pm each day. Traffic will be diverted via Birkdale.

Feedback: Let us know how we did by leaving us feedback.