High Street, Rye - Kerbing & Carriageway Repairs

20th January - 21st February 2020

High Street, Rye - Kerbing & Carriageway Repairs

What works are taking place?

We will be carrying out kerbing and carriageway repairs on High Street, Rye.

When will these works start?

Kerbing
20-28 January 2020
Work to be carried out under a night-time road closure.

Carriageway Repairs
17-21 February 2020
Work to be carried out under a night-time road closure.

Road closure information

High Street will be closed to through traffic between 6pm and 6am each night from Landgate to Mermaid Street.

Diversion

Traffic will be diverted via Landgate, Fishmarket Road, South Undercliff and vice versa.

Information for local people

Vehicle access: The road will be closed to through traffic. This is for your safety and the safety of our workers. If you do need vehicle access then please discuss this with the team on site. We will try to give access where we can but there may be long delays whilst we make the area safe. We will always allow access for emergency vehicles. Pedestrian access will be maintained.

Weather: If it rains, we might be delayed in our works. We will keep you updated with any changes via advance warning signs.

Parking: Please park your vehicle off road or in another location, otherwise your vehicle may be towed away. There will be ‘no parking’ signs and cones on site to advise where parking is restricted.

Buses: We apologise if our works cause disruption to your bus service. Please check with the bus company for any alterations to the service during this time.

Feedback: Let us know how we did by leaving us feedback.