Michelham Priory Road, Arlington - Footway Surfacing

13-18 & 25-27 October 2021

Scheme Location:

Michelham Priory Road, Arlington - Footway Surfacing

Scheme Information:

What works are taking place?

We will be carrying out footway surfacing works on Michelham Priory Road, Arlington.

When will these works start?

The prep works are scheduled to take place between 13th & 18th October 2021 and the surfacing works are provisionally scheduled for 25th to 27th October 2021.

These works are extremely weather dependent and therefore dates are subject to change. We will update our website and signage on site with any date changes.

Road closure information

The road will remain open during the prep works.

During the surfacing works, Michelham Priory Road will be closed between 7am & 7pm each day from Coldharbour Road to Caneheath.

Information for local people

Pedestrian access may be restricted at times as we may close sections of the footway to allow us to work.

Pedestrian access will also be restricted as we allow the footway to dry. Walking on it when wet could damage your shoes, so please wait for the footway to reopen before using it.

If in doubt, please speak to the team on site who will be able to help.

Feedback: Let us know how we did by leaving us feedback.