Ridgewood Development Uckfield - UKPN Works

January - May 2021

Location:


Ridgewood Development Uckfield - UKPN Works

Scheme Information:

These works are being carried out by UK Power Networks - They can be contacted on 0800 028 4587 or care@ukpowernetworks.co.uk

What works are taking place?

Provision of a new 33kv electricity supply including duct laying, box building, cable installation and jointing works for the Ridgewood Development Uckfield.

When will these works start?

Works will commence in Bell Lane 11th January 2021, through to the High Street, through to New Town, through to Lewes road and are due for completion May 2021.

Traffic Management

There will be one set of works, utilising two/three or multiway Temporary Traffic signals depending on the location throughout the project.

Working Hours

Monday to Friday 7.00-19.00

Sat 8.00-17.00

Sun 9.00-13.00

Works may be undertaken outside of these hours providing they comply with environmental noise levels.