The Ridge, Hastings - Pedestrian Crossing Construction

Monday 25th January 2021 for 11 weeks

Scheme Location:


The Ridge, Hastings - Pedestrian Crossing Construction

Scheme Information:

What works are taking place?

We will be constructing a signalised pedestrian crossing on The Ridge adjacent to Hastings Court Care Home and installing a bus stop adjacent to Saint Helen’s Church for west bound services.

When will these works start?

Work will start on Monday 25th January 2021 and continue for up to 11 weeks.

Traffic Management

The Ridge will remain open with temporary traffic lights in place.

Chowns Hill will be closed for the duration of the works between The Ridge & Denehurst Gardens.

The bus stop at the junction with Chowns Hill will be suspended for the duration of the works.

Diversion for Chowns Hill

Diversion for the Chowns Hill closure: The Ridge, Old London Road, Rye Road, Rock Lane, Ivyhouse Lane & vice versa.

Feedback: Let us know how we did by leaving us feedback.