Tidebrook Road, Wadhurst - Wall Repairs

Monday 28th June 2021 for 20 weeks

Scheme Location:


Tidebrook Road, Wadhurst - Wall Repairs

Scheme Information:

What works are taking place?

We will be carrying out retaining wall repairs on Tidebrook Road, Wadhurst.

When will these works start?

Work will start on Monday 28th June 2021 and continue until Friday 12th November 2021.

For the first 2 weeks, Clancy Docwra will be working on behalf of South East Water to divert the water main.

BT will be working to divert overhead cables during the third week.

We are aiming to start our works on Monday 19th July 2021.If this changes we will update the signage on site.

Road closure information

Tidebrook Road will be closed to through traffic 24 hours a day between Towngate Farm & Eastfield Cottages. If you do need vehicle access then please discuss this with the team on site. We will try to give access where we can but there may be delays whilst we make the area safe. We will always allow access for emergency vehicles.

Diversion

Traffic will be diverted via Tidebrook Road, Lake Street, Mayfield Road A267, Wadhurst Road B2100 & vice versa.