A271 Upper Horsebridge, Hailsham - Essential Gas Works

11/01/2021 – 14/03/2021 

Scheme Location:


A271 Upper Horsebridge, Hailsham - Essential Gas Works

Scheme Information:

What works are taking place?

Essential replacement of old metal gas mains with new plastic pipes. This is a safety-critical project that needs to be carried out to ensure the local community continues to receive a safe and reliable gas supply.

Location: From the junction London Road to 100 Upper Horsebridge

When will these works start?

Monday 11th January 2021 and will continue until 14th March 2021

Traffic Management

Traffic signals – manually controlled between the hours of 07:00 – 19:00 Monday to Saturday

Programme of works:

• w/c 11th Jan. Set-up 3way lights j/w London Rd and set-up compound, excavate camera holes and camera first section of main.

• w/c 18th Jan. Excavate connection / service holes and live insert main.

• w/c 25th Jan. Relay services and reinstate 1st phase.

• w/c 1st Feb. Set-up two way lights, excavate camera holes and camera second section of main.

• w/c 8th Feb Excavate connection / service holes and live insert main.

• w/c 15th Feb relay services and reinstate.

• w/c 22nd Feb set-up 2way lights and pedestrian crossing system. Excavate camera holes and camera third section of main.

• w/c 1st March relay services and dead insert (winch)

• w/c 8th March reinstate and excavate in footway to abandon final section of main. Clear site by 14th March