NameTownHighway AssetRoad NumberType of WorkProvisional DateCompleted
WhitewayAlfristonCarriageway C39Surface Treatment (Including Preperation works)25/06/2021
Horseshoe LaneBeckleyCarriageway U6415Carriageway Jointing and Crack Infill programme 13/07/2021Completed
Two HovensBeckleyCarriageway A268Preservation Treatments 01/09/2021
Whitebread LaneBeckleyCarriageway A268Preservation Treatments 01/09/2021
Station Road Berwick Carriageway C39Preservation Treatments 01/09/2021
Ashby CloseBexhillCarriageway U6711Concrete rehabilitation works 21/06/2021Completed
Blackmill CloseBexhillCarriageway U6711Concrete rehabilitation works 07/07/2021Completed
Cooden Sea Road BexhillCarriageway B2182Preservation Treatments 01/09/2021
Davis CloseBexhillCarriageway U6711Concrete rehabilitation works 21/06/2021Completed
Millwood RoadBexhillCarriageway U6711Concrete rehabilitation works 09/06/2021Completed
Mount Idol ViewBexhillCarriageway U6711Concrete rehabilitation works 14/06/2021Completed
Ninfield RoadBexhillCarriageway A269Preservation Treatments 01/09/2021
Pankhurst RiseBexhillCarriageway U6711Concrete rehabilitation works 23/06/2021Completed
Paton RoadBexhillCarriageway U6711Concrete rehabilitation works 10/06/2021Completed
Putlands CrescentBexhillCarriageway U6711Concrete rehabilitation works 07/07/2021Completed
Jubilee Road Bexhill Carriageway U6711Concrete rehabilitation works 16/06/2021Completed
Southlands Road Bexhill Carriageway U6711Concrete rehabilitation works 28/06/2021Completed
Lewes Road Blackboys Carriageway B2192Preservation Treatments 01/09/2021
Cackle StreetBredeCarriageway A28Preservation Treatments 01/09/2021
Udimore RoadBredeCarriageway B2089Surface Treatment (Including Preperation works)24/06/2021Completed
Burwash RoadBroad OakCarriageway A265Surface Treatment (Including Preperation works)16/06/2021Completed
Beechwood LaneCooksbridgeCarriageway Carriageway Jointing and Crack Infill programme 28/05/2021Completed
Beechwood LaneCooksbridgeCarriageway C6Surface Treatment (Including Preperation works)28/05/2021Completed
Cooksbridge Road (The A275)CooksbridgeCarriageway A275Carriageway structural Mar / Apr
High Street Cross in Hand Carriageway B2102Preservation Treatments 01/09/2021
Alexandra RoadEastbourneCarriageway U2179Carriageway Jointing and Crack Infill programme 15/07/2021Completed
Allfrey RoadEastbourneCarriageway U2179Carriageway Jointing and Crack Infill programme 20/07/2021Completed
Blakes Way EastbourneCarriageway U2192Carriageway Jointing and Crack Infill programme 14/07/2021Completed
Cavendish PlaceEastbourneCarriageway U2146Carriageway structural Sep / Oct
Compton Drive EastbourneCarriageway U2032Surface Treatment (Including Preperation works)07/06/2021Completed
Kings Close EastbourneCarriageway U2118Carriageway Jointing and Crack Infill programme 16/07/2021Completed
Lottbridge Drove (Nbound)EastbourneCarriageway A2290Carriageway structural Sep / Oct
Pevensey RoadEastbourneCarriageway A259Carriageway Jointing and Crack Infill programme Spring '21
Saxon Place EastbourneCarriageway U2083Carriageway Jointing and Crack Infill programme Spring '21
St Annes Service RoadEastbourneCarriageway U2129Carriageway Jointing and Crack Infill programme Spring '21
Whitley RoadEastbourneCarriageway A2021Preservation Treatments 01/09/2021
Blackwater Road Eastbourne Carriageway U2056Preservation Treatments 01/09/2021
Hazelwood Avenue Eastbourne Carriageway U2248Preservation Treatments 01/09/2021
Lottbridge Drove (Sbound)Eastbourne Carriageway A2290Preservation Treatments 01/09/2021
Mountfield Roundabout Eastbourne Carriageway U2236Preservation Treatments 01/09/2021
Pevensey Bay RoadEastbourne Carriageway A259Preservation Treatments 01/09/2021
Priory Road Eastbourne Carriageway U2199Preservation Treatments 01/09/2021
A265 (Haremere Hill)EtchinghamCarriageway A265Carriageway structural 06/04/2021Completed
A265 (Straight Mile)EtchinghamCarriageway A265Carriageway structural 12/04/2021Completed
Hawkhurst RoadFlimwellCarriageway A268Surface Treatment (Including Preperation works)03/06/2021Completed
Colemans Hatch RoadForest RowCarriageway C2Surface Treatment (Including Preperation works)16/06/2021Completed
Holtye Road & Colestock RoadForest RowCarriageway A264Preservation Treatments 01/09/2021
Lewes Road Forest RowCarriageway A22Carriageway Jointing and Crack Infill programme 09/08/2021
Edenbridge RoadHartfieldCarriageway B2026Surface Treatment (Including Preperation works)11/06/2021Completed
Combe Valley Way HastingsCarriageway A2690Preservation Treatments 01/09/2021
Elphinstone RoadHastingsCarriageway C212Carriageway structural 21/06/2021Completed
Harley Shute RoadHastingsCarriageway B2092Carriageway structural Oct / Nov
Old London Road/Rye Road Hastings Carriageway A259Preservation Treatments 01/09/2021
The Ridge Hastings Carriageway B2093Preservation Treatments 01/09/2021
West EndHerstmonceuxCarriageway C344Carriageway structural 19/07/2021
High StreetHoramCarriageway B2203Carriageway structural Oct / Nov
Coopers Corner Hurst Green Carriageway A229Surface Treatment (Including Preperation works)16/06/2021Completed
Pett Level Road / Sea RoadIckleshamCarriageway U7769Carriageway structural 01/06/2021
The DickerLaughtonCarriageway A22Surface Treatment (Including Preperation works)24/05/2021Completed
Neville RoadLewesCarriageway A275Preservation Treatments 01/09/2021
North StreetLewesCarriageway A2029Carriageway Jointing and Crack Infill programme 26/07/2021
Winterbourne Hollow LewesCarriageway C7Preservation Treatments 01/09/2021
Rotherfield LaneMayfieldCarriageway U7576Carriageway Jointing and Crack Infill programme 12/07/2021Completed
South WayNewhavenCarriageway A259Carriageway structural 21/06/2021
Catsfield RoadNinfieldCarriageway B2204Preservation Treatments 01/09/2021
Rye RoadNorthiamCarriageway B2088Preservation Treatments 01/09/2021
Main Street Northiam Carriageway A28Preservation Treatments 01/09/2021
South Coast Road Peacehaven Carriageway A259Carriageway structural 12/07/2021
Wartling RoadPevenseyCarriageway C17Surface Treatment (Including Preperation works)25/06/2021
Farmlands WayPolegateCarriageway U7930Concrete rehabilitation works 01/06/2021
High StreetPolegateCarriageway C40Preservation Treatments 01/09/2021
High StreetRyeCarriageway U4637Carriageway structural Sep / Oct
St Marys LaneSidleyCarriageway U6708Surface Treatment (Including Preperation works)18/06/2021Completed
Warrior SquareSt LeonardsCarriageway U3160Carriageway structural 06/09/2021
London Road St Leonards Carriageway A2102Preservation Treatments 01/09/2021
South Coast Road Telscombe Carriageway A259Carriageway structural 12/07/2021
Nevill RoadUckfieldCarriageway U7769Carriageway structural 26/07/2021
Udimore RoadUdimoreCarriageway B2089Surface Treatment (Including Preperation works)24/06/2021Completed
Mayfield LaneWadhurstCarriageway B2100 Surface Treatment (Including Preperation works)07/06/2021Completed
Rattle RoadWesthamCarriageway C712Preservation Treatments 01/09/2021
Hooks BeachWhatlingtonCarriageway B2089Carriageway Jointing and Crack Infill programme 16/08/2021
Hundred Acre LaneWivelsfieldCarriageway Carriageway Jointing and Crack Infill programme 05/07/2021Completed