Below is our planned works programme for 2021/22. This includes all major works planned by East Sussex Highways. You can find all other works carried out by other parties here, such as utilities.
Please note that dates are provisional.
This list is ordered alphabetically, by Town/Parish.
More information about the type of work being carried out can be found at the bottom of this page.
Name | Town | Highway Asset | Road Number | Type of Work | Provisional Date | Completed |
---|---|---|---|---|---|---|
Horseshoe Lane | Beckley | Carriageway | U6415 | Carriageway Jointing and Crack Infill programme | 13/07/2021 | Completed |
Ashby Close | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 21/06/2021 | Completed |
Blackmill Close | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 07/07/2021 | Completed |
Davis Close | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 21/06/2021 | Completed |
Millwood Road | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 09/06/2021 | Completed |
Mount Idol View | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 14/06/2021 | Completed |
Pankhurst Rise | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 23/06/2021 | Completed |
Paton Road | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 10/06/2021 | Completed |
Putlands Crescent | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 07/07/2021 | Completed |
Jubilee Road | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 16/06/2021 | Completed |
Southlands Road | Bexhill | Carriageway | U6711 | Concrete rehabilitation works | 28/06/2021 | Completed |
Burwash Road | Broad Oak | Carriageway | A265 | Surface Treatment (Including Preperation works) | 16/06/2021 | Completed |
Beechwood Lane | Cooksbridge | Carriageway | Carriageway Jointing and Crack Infill programme | 28/05/2021 | Completed | |
Beechwood Lane | Cooksbridge | Carriageway | C6 | Surface Treatment (Including Preperation works) | 28/05/2021 | Completed |
High Street | Cross in Hand | Carriageway | B2102 | Preservation Treatments | 21/10/2021 | Completed |
Alexandra Road | Eastbourne | Carriageway | U2179 | Carriageway Jointing and Crack Infill programme | 15/07/2021 | Completed |
Allfrey Road | Eastbourne | Carriageway | U2179 | Carriageway Jointing and Crack Infill programme | 20/07/2021 | Completed |
Blakes Way | Eastbourne | Carriageway | U2192 | Carriageway Jointing and Crack Infill programme | 14/07/2021 | Completed |
Cavendish Place | Eastbourne | Carriageway | U2146 | Carriageway structural | 13/09/2021 | Completed |
Compton Drive | Eastbourne | Carriageway | U2032 | Surface Treatment (Including Preperation works) | 07/06/2021 | Completed |
Kings Close | Eastbourne | Carriageway | U2118 | Carriageway Jointing and Crack Infill programme | 16/07/2021 | Completed |
Blackwater Road | Eastbourne | Carriageway | U2056 | Preservation Treatments | 08/10/2021 | Completed |
Lottbridge Drove (Sbound) | Eastbourne | Carriageway | A2290 | Preservation Treatments | 05/10/2021 | Completed |
Mountfield Roundabout | Eastbourne | Carriageway | U2236 | Preservation Treatments | 29/09/2021 | Completed |
A265 (Haremere Hill) | Etchingham | Carriageway | A265 | Carriageway structural | 06/04/2021 | Completed |
A265 (Straight Mile) | Etchingham | Carriageway | A265 | Carriageway structural | 12/04/2021 | Completed |
Hawkhurst Road | Flimwell | Carriageway | A268 | Surface Treatment (Including Preperation works) | 03/06/2021 | Completed |
Colemans Hatch Road | Forest Row | Carriageway | C2 | Surface Treatment (Including Preperation works) | 16/06/2021 | Completed |
Holtye Road & Colestock Road | Forest Row | Carriageway | A264 | Preservation Treatments | 14/10/2021 | Completed |
Lewes Road | Forest Row | Carriageway | A22 | Carriageway Jointing and Crack Infill programme | 09/08/2021 | Completed |
Edenbridge Road | Hartfield | Carriageway | B2026 | Surface Treatment (Including Preperation works) | 11/06/2021 | Completed |
Combe Valley Way | Hastings | Carriageway | A2690 | Preservation Treatments | 20/09/2021 | Completed |
Elphinstone Road | Hastings | Carriageway | C212 | Carriageway structural | 21/06/2021 | Completed |
Harley Shute Road | Hastings | Carriageway | B2092 | Carriageway structural | 25/10/2021 | Completed |
Coopers Corner | Hurst Green | Carriageway | A229 | Surface Treatment (Including Preperation works) | 16/06/2021 | Completed |
Pett Level Road / Sea Road | Icklesham | Carriageway | U7769 | Carriageway structural | 01/06/2021 | Completed |
The Dicker | Laughton | Carriageway | A22 | Surface Treatment (Including Preperation works) | 24/05/2021 | Completed |
Neville Road | Lewes | Carriageway | A275 | Preservation Treatments | 09/09/2021 | Completed |
North Street | Lewes | Carriageway | A2029 | Carriageway Jointing and Crack Infill programme | 26/07/2021 | Completed |
Rotherfield Lane | Mayfield | Carriageway | U7576 | Carriageway Jointing and Crack Infill programme | 12/07/2021 | Completed |
South Way | Newhaven | Carriageway | A259 | Carriageway structural | 23/06/2021 | Completed |
South Coast Road | Peacehaven | Carriageway | A259 | Carriageway structural | 12/07/2021 | Completed |
Farmlands Way | Polegate | Carriageway | U7930 | Concrete rehabilitation works | 01/06/2021 | Completed |
High Street | Polegate | Carriageway | C40 | Preservation Treatments | 23/09/2021 | Completed |
High Street | Rye | Carriageway | U4637 | Carriageway structural | 28/03/2022 | |
St Marys Lane | Sidley | Carriageway | U6708 | Surface Treatment (Including Preperation works) | 18/06/2021 | Completed |
London Road | St Leonards | Carriageway | A2102 | Preservation Treatments | 14/09/2021 | Completed |
South Coast Road | Telscombe | Carriageway | A259 | Carriageway structural | 12/07/2021 | Completed |
Nevill Road | Uckfield | Carriageway | U7769 | Carriageway structural | 26/07/2021 | Completed |
Mayfield Lane | Wadhurst | Carriageway | B2100 | Surface Treatment (Including Preperation works) | 07/06/2021 | Completed |
Hooks Beach | Whatlington | Carriageway | B2089 | Carriageway Jointing and Crack Infill programme | 16/08/2021 | Completed |
Hundred Acre Lane | Wivelsfield | Carriageway | Carriageway Jointing and Crack Infill programme | 05/07/2021 | Completed | |
West End | Herstmonceux | Carriageway | C344 | Carriageway structural | 26/07/2021 | Completed |
Udimore Road | Udimore | Carriageway | B2089 | Surface Treatment (Including Preperation works) | 24/06/2021 | Completed |
Udimore Road | Brede | Carriageway | B2089 | Surface Treatment (Including Preperation works) | 24/06/2021 | Completed |
Wartling Road | Pevensey | Carriageway | C17 | Surface Treatment (Including Preperation works) | 25/06/2021 | Completed |
Whiteway | Alfriston | Carriageway | C39 | Surface Treatment (Including Preperation works) | 25/06/2021 | Completed |
Warrior Square | St Leonards | Carriageway | U3160 | Carriageway structural | 06/09/2021 | Completed |
Lottbridge Drove (Nbound) | Eastbourne | Carriageway | A2290 | Carriageway structural | 06/09/2021 | |
High Street | Horam | Carriageway | B2203 | Carriageway structural | 06/09/2021 | Completed |
Cooksbridge Road (The A275) | Cooksbridge | Carriageway | A275 | Carriageway structural | 06/09/2021 | Completed |
Saxon Place | Eastbourne | Carriageway | U2083 | Carriageway Jointing and Crack Infill programme | 06/10/2021 | Completed |
Priory Road | Eastbourne | Carriageway | U2199 | Preservation Treatments | 19/10/2021 | Completed |
Rattle Road | Westham | Carriageway | C712 | Preservation Treatments | 24/09/2021 | Completed |
Rye Road | Northiam | Carriageway | B2088 | Preservation Treatments | 13/10/2021 | Completed |
Whitebread Lane | Beckley | Carriageway | A268 | Preservation Treatments | 11/10/2021 | Completed |
Winterbourne Hollow | Lewes | Carriageway | C7 | Preservation Treatments | 09/09/2021 | Completed |