A22 Hailsham Bypass - Jointing

Monday 10th September for 5 nights


What works are taking place?

We will be carrying out carriageway jointing works on A22 Hailsham Bypass.

Work will start on Monday 10th September 2018 and continue for up to 5 days/nights.

Road closure information

The road will be closed in phases between 8pm and 6am to minimise disruption.

DAY 1 (9.30am-3.30pm): Cophall Roundbout to Eagles Roundabout.
Carriageway Improvement Works - Lane closure (1 lane at a time).

NIGHT 1 (8pm-6am): Cophall Roundabout to Eagles Roundabout.
Jointing Works. Road closed (northbound & southbound).

DAY 2 (9.30am-3.30pm): Diplocks to Eagles Roundabout.
Carriageway Improvement Works - Lane closure (1 lane at a time).

NIGHT 2 (8pm-6am): Diplocks to Eagles Roundabout.
Jointing Works. Road closed (northbound & southbound).

DAY 3 (9.30am-3.30pm): Boship Roundabout to Diplocks.
Carriageway Improvement Works - Lane closure (1 lane at a time).

NIGHT 3 (8pm-6am): Boship Roundabout to Diplocks.
Jointing Works. Road closed (northbound & southbound).

Wet weather may delay works.

Diversion

Suitable diversion routes will be signed on site for each day.