Arundel Road, Peacehaven - Carriageway Jointing

Monday 23rd September 2019 for 5 Days

What works are taking place?

We will be carrying out carriageway jointing works on Arundel Road, Peacehaven.

When will these works start?

Work will start on Monday 23rd September 2019 and continue for 5 days.

Road closure information

Arundel Road will be closed to through traffic between 7am and 7pm from Greenwich Way to Cissbury Avenue.

Access for residents will be maintained as much as possible.

We will be working in 300 metre sections to minimise disruption.

Diversion

Traffic will be diverted via Sutton Avenue, South Coast Road and vice versa.

Information for local people

Vehicle access: The road will be closed to through traffic. This is for your safety and the safety of our workers. If you do need vehicle access then please discuss this with the team on site. We will try to give access where we can but there may be long delays whilst we make the area safe. We will always allow access for emergency vehicles. Pedestrian access will be maintained.

Weather: If it rains, we might be delayed in our works. We will keep you updated with any changes via advance warning signs.

Parking: Please park your vehicle off road or in another location, otherwise your vehicle may be towed away. There will be ‘no parking’ signs and cones on site to advise where parking is restricted.

Buses: We apologise if our works cause disruption to your bus service. Please check with the bus company for any alterations to the service during this time.

Bin Collections: We have informed your local council about these works. Your local District or Borough Council will let you know if there are any changes to your collection.

Feedback: Let us know how we did by leaving us feedback.