Battle Road/Queensway, Hastings - Bridge Repairs

Monday 14th October 2019 for 6 weeks

What works are taking place?

We will be carrying out bridge repairs on Battle Road, Hastings.

When will these works start?

Work will start on Monday 14th October 2019 and continue for 6 weeks.

Road Closure & Traffic Management

Temporary traffic lights will be in place for the duration of the works. The lights will be manually controlled during peak hours to minmise disruption.

Due to the nature of the works, we will need to close Queensway at the bridge from Monday 14th October until Monday 21st October 2019 (8pm-6am). 

A suitable diversion will be signed on site via The Ridge West, Junction Road, Sedlescombe Road North, Old Harrow Road, Ashbrook Road, Blackman Avenue, Ironlatch Avenue, Crowhurst Road, Queensway and vice versa.

Elements of these works will be noisy. We apologise for any inconvenience this causes.

Information for local people

Weather: If it rains, we might be delayed in our works. We will keep you updated with any changes via advance warning signs.