Lea Avenue, Rye - Drainage Works

Monday 25th March 2019 for 1 day

What works are taking place?

We will be carrying out drainage works on Lea Avenue, Rye.

When will these works start?

Work will start on Monday 25th March 2019 and continue for 1 day.

Road closure information

Lea Avenue will be closed to through traffic between 8am and 4.30pm from Ferring Close to Pottingfield Road. We will be working outside numbers 21 & 23.

Diversion

Traffic will be diverted via Pottingfield Road, Lea Avenue and vice versa.

Information for local people

Vehicle access: The road will be closed to through traffic. This is for your safety and the safety of our workers. If you do need vehicle access then please discuss this with the team on site. We will try to give access where we can but there may be long delays whilst we make the area safe. We will always allow access for emergency vehicles. Pedestrian access will be maintained.

Weather: If it rains, we might be delayed in our works. We will keep you updated with any changes via advance warning signs.

Parking: Please park your vehicle off road or in another location, otherwise your vehicle may be towed away. There will be ‘no parking’ signs and cones on site to advise where parking is restricted.

Buses: We apologise if our works cause disruption to your bus service. Please check with the bus company for any alterations to the service during this time.

Bin Collections: We have informed your local council about these works. Your local District or Borough Council will let you know if there are any changes to your collection.

Feedback: Let us know how we did by leaving us feedback.