A259 Seaside, Eastbourne - Junction Improvement Works

Monday 11th March 2019 for 8 days

What works are taking place?

We will be carrying out junction improvement works on the junction of Seaside/Beamsley Road/Whitley Road.

Works will include:

• Removal of the push button units and replacement of the traffic signal poles at the Seaside (south) crossing point.

• Removal of tactile slabs within the Seaside (south) central island and replacement with tarmac.

• Installation of a new recessed manhole cover at the crossing on Beamsley Road.

• Footway tidying works along Seaside.

• Carriageway lining.

When will these works start?

Work will start on Monday 11th March 2019 and continue for 8 days.

Traffic Management

The road will remain open with temporary traffic lights in place. The lights will be manually controlled between 7am & 7pm.

On Monday 18th March we will be working from 7pm to midnight.