The Ridge Hastings - Bus-Stop Improvements

Monday 9th September 2019 for 6 weeks

What works are taking place?

We will be carrying out bus stop improvement works on The Ridge, Hastings.

When will these works start?

Work will start on Monday 9th September 2019 and continue for 6 weeks.

Traffic Management

B2093 The Ridge will remain open with temporary traffic lights in place. The lights will be manually controlled during peak hours.

Bus Stops Affected - The bus stops listed below will be closed during the periods shown.

Helenswood Leisure Centre (e-bound) 9-11 September (Off Peak) & 18 October (Night)

Helenswood Leisure Centre (w-bound) 12-13 September (Off Peak) & 18 October (Night)

Maitland Close (w-bound) 16-17 September (Off Peak) & 18 October (Night)

Maitland Close (e-bound) 18-23 September (Off Peak) & 18 October (Night)

Sandrock Park (e-bound) 24-25 September (Off Peak) & 18 October (Night)

Sandrock Park (w-bound) 26-27 September (Off Peak) & 19 October (Night)

St Anne’s House (w-bound) 30 September-8 October (Off Peak) & 17 October (Night)

Maplehurst Road (w-bound) 3-17 October (nights)

Maplehurst Road (e-bound) 15-18 October (nights) 

Information for local people

Some night works will be required at each stop. We apologise for any inconvenience this causes