Tunbridge Wells Road, Mark Cross - Kerbing and Resurfacing

Kerbing: 12 - 28 September // Resurfacing 30 October - 3 November

What works are taking place?

We will be carrying out kerb repairs & carriageway resurfacing on Tunbridge Wells Road, Mark Cross.

When will these works start?


Kerb Repairs will start on Wednesday 12th September 2018 and continue for 13 days. The road will remain open with temporary 2-way traffic lights located north of the junction with Brickyard Lane. Lights will be manually operated during peak hours.


Resurfacing will start on Tuesday 30th October 2018 and continue for 5 nights. The road will be closed to through traffic from B2100 junction to B2099 junction between 8pm and 6am. Traffic will be diverted via B2099, Bunny Lane, A26, A26 Budletts Rbt, A272 Buxted, A267 & Vice Versa.