Victoria Drive, Eastbourne - Zebra Crossing Refurbishment

Monday 8th July 2019 for 5 weeks



What works are taking place?

We will be carrying out improvement works to the zebra crossings at the locations shown on Victoria Drive, Eastbourne.

When will these works start?

Work will start on Monday 8 July 2019 and continue for 5 weeks. Some night working will be involved.

Schedule of Works

Phase 1 - 08/07 to 06/08 - Southern Crossing

• 3-way lights will be in operation on Victoria Drive. The lights will be manually controlled during peak hours.

• Milton Road will be closed at the junction with Victoria Drive during this phase. A suitable diversion route will be signed.

• Green Street & Beechy Avenue junctions will be closed 05/08 for 3 nights (8pm-6am) while we carry out surfacing and lining works.


Phase 2 - 06/08 to 10/08 - Northern Crossing

• 2-way lights will be in operation on Victoria Drive at the junction with Eldon Road. The lights will be manually controlled during peak hours.

• Eldon Road, Wessex Place & Central Avenue will be closed at their junctions with Victoria Drive 08/08 for 3 nights (8pm-6am) while we carry out surfacing and lining works. A suitable diversion route will be signed.